Site Management of Work-in-Process Buffers to Enhance Project Performance Using the Reliable Commitment Model: Case Study
Loading...
Date
2011
Journal Title
Journal ISSN
Volume Title
Publisher
ASCE-AMER SOC CIVIL ENGINEERS
Abstract
Buffers have been commonly used as a production strategy to protect construction processes from the negative impact of variability. Construction practitioners and researchers have proposed several buffering approaches for different production situations and contexts. However, these solutions have been impractical for managing buffers. To overcome this, this study proposes a new site methodology for managing work-in-process (WIP) buffer in repetitive projects, on the basis of the reliable commitment model (RCM). RCM is a decision-making tool based on lean principles, which uses statistical models to develop more reliable work plans at the operational level. RCM helps to manage WIP buffer in work plans by using site information and planning reliability indicators that result in improved project performance, such as labor productivity and process progress. A repetitive building project was used as a case study. The main finding was that labor productivity, process progress, and waiting times improved when using larger WIP buffers than those typically used among crews. This shows the potential of RCM as a practical tool to manage WIP buffer sizes and to promote the use of lean production strategies at the operational level. DOI: 10.1061/(ASCE)CO.1943-7862.0000346. (C) 2011 American Society of Civil Engineers.
Description
Keywords
Buffers, Labor productivity, Lean production, Reliable commitment model, Repetitive building projects, Work-in-process, CONSTRUCTION, VARIABILITY, RELIABILITY